OBJECTIVE
Execute T-38C simulated refueling as receiver, adapting joins for approach, contacts, and emergencies while emphasizing position stability, communications, and breakaway procedures without actual boom hardware.
CONTENT
Receiver Approach Procedures
- • Closure control: Manage overtake rate during approach.
- • Override: Slight power addition if falling behind.
- • Approach speed: 350 KCAS, 45° bank intercept max.
- • Observation position: 500 ft, 30° bearing from tanker.
RECEIVER APPROACH PARAMETERS
Approach Speed: 350 KCAS
Max Bank: 45°
Obs Position: 500 ft/30°
Closure: 10-20 kts
Contact Procedures
- • Normal contact: Smooth transition from pre-contact to contact position.
- • Override contact: Aggressive join when time-critical.
- • Pilot director lights: Follow tanker's PDL for position guidance.
- • Stability: Small, smooth corrections - avoid overcontrolling.
PILOT DIRECTOR LIGHTS (PDL)
GREEN
On position
AMBER
Correction needed
RED
Breakaway
Disconnect Procedures
- • Normal disconnect: Tanker initiates, receiver maintains position until clear.
- • Receiver disconnect: Request via radio if needed.
- • Post-disconnect: Smooth transition to observation or depart.
Contingencies
- • Breakaway: Immediate separation on tanker call or safety concern.
- • Boom instability: Excessive azimuth/elevation movements require disconnect.
- • Turbulence: Moderate-severe may require spacing increase or abort.
- • Lost comm: Follow visual signals, RTB if unable.
RECEIVER BREAKAWAY
- Tanker calls "Breakaway x3" and flashes lights
- Receiver: Throttle IDLE
- Receiver: Speed brakes OUT
- Receiver: Descend clear of tanker flight path
- Maintain visual, await rejoin clearance
Procedures
- • Radio/visual signals: PDL interpretation, verbal backup.
- • Turbulence awareness: Adjust technique for conditions.
- • AGSM: Awareness during maneuvering phases.
- • Deconfliction: Maintain safe separation during all phases.
- • Track planning: Coordinate with tanker for refueling windows.
COMPLETION STANDARDS
Trainees will demonstrate understanding through oral quizzing. Must be able to:
- • Explain receiver approach procedures and parameters
- • Describe contact procedures including PDL interpretation
- • Explain breakaway procedures and contingencies
- • Describe simulation adaptations (stable formation = "contact")
Completion: Demonstrate understanding via oral quizzing per vTAC vAETC standards